Friday, October 30, 2020

Update 10.30.20

 Since my last update, framing and insulation is underway in the classroom addition. Mechanical, plumbing and electrical is being installed throughout the project. The roof is nearly ready for shingles. The chiller has been installed to provide cooling for the building and work is underway to build out the boiler room. Sheetrock is being hung throughout the project. Tile will be installed in the locker rooms soon. Lockers are installed and painting is underway in areas that are ready for it. Iron work railings are installed in the gym.

We anticipate moving existing furniture into the new classroom spaces in early January in preparation for students coming back to the building. While some classes will continue to meet in the old classroom wing, many will be taught in the new classrooms while the remodeling of the interior of the building is underway. We remain on schedule and on budget.

If you're interested in walking through the project, please contact me and I'll arrange for you to participate in the next available tour.